31N Tower

31N Tower

The tower is one of the tallest skyscrapers in the New Capital,  The construction of the tower started in 2021 and is expected to be completed by December 2025

31 North Tower construction updates

updated on 16/12/2023
- 70% of the tower’s concrete structure has been completed - The construction of 18 floors has been completed - A new floor is built only every 18 days - More than 150 workers daily
Remaining to be completed: